title: "Resolution 022"
|
|
|
|
|
---
|
|
|
|
|
|
|
|
|
|
- Topic: Budget XXX: Abra integration suite automation
|
|
|
|
|
- Date: ...
|
|
|
|
|
- Deadline: ...
|
|
|
|
|
- Size: Medium
|
|
|
|
|
|
|
|
|
|
### Summary
|
|
|
|
|
|
|
|
|
|
Motivated by the collective release planning: [`#583`](https://git.coopcloud.tech/coop-cloud/organising/issues/583) under "Automate Integration Test Suite".
|
|
|
|
|
|
|
|
|
|
The latest `abra` release (`0.9.x`) was heavily delayed due to several issues.
|
|
|
|
|
One of those was the need to fix the integration test suite which wasn't run in
|
|
|
|
|
some time. Many breakages had crept into the test suite over time. This can
|
|
|
|
|
avoided in the future by automating the running of the integration test suite.
|
|
|
|
|
|
|
|
|
|
This proposal describes a way to do this and includes a budget for doing so.
|
|
|
|
|
|
|
|
|
|
### Details (Budget XXX)
|
|
|
|
|
|
|
|
|
|
The `abra` test suite takes around 1.30 hrs to run on a modest machine.
|
|
|
|
|
Therefore, we propose to run it only once daily. Some parts of the tests are
|
|
|
|
|
slow, fast and only a few require public DNS. This means we can break up the
|
|
|
|
|
tests and run them in separate "builds" to speed things up. This involves some
|
|
|
|
|
research & experimentation.
|
|
|
|
|
|
|
|
|
|
Also, we need a server to run the tests on. This machine should be wiped clean
|
|
|
|
|
each day (`docker <command> prune ....`) and have the usual DNS machinery
|
|
|
|
|
attached to it, e.g. `int.coopcloud.tech`, `*.int.coopcloud.tech`. Ideally some
|
|
|
|
|
federation members will also be provided shell access with root permissions.
|
|
|
|
|
|
|
|
|
|
Once all this is wired up, we can implement the CI/CD configuration to make the
|
|
|
|
|
test suite run automatically once a day. This will be triggered via the
|
|
|
|
|
`.drone.yml` in the `abra` Git repository.
|
|
|
|
|
|
|
|
|
|
Budget details:
|
|
|
|
|
|
|
|
|
|
| Item | Cost | Who? |
|
|
|
|
|
| ---- | ---- | ---- |
|
|
|
|
|
| Server | ??? | ??? |
|
|
|
|
|
| Server setup | 2 hrs | `@d1` |
|
|
|
|
|
| R&D for breaking up tests | 5 hrs | `@d1` |
|
|
|
|
|
| Implementing CI configs | 10 hrs | `@d1` |
|
|
|
|
|
|
|
|
|
|
**NOTE**: budget for server includes yearly costs of server and ongoing maintenance.
|